Design - Build Taji Bulk Fuel Facility . Taji Air Base / Iraq

Project value

$2,966,800

Role of Company

Prime

Project duration

365 days

Status of Project

Completed Successfully

Project location

Iraq- Taji base

 

This project was awarded by USAF and administrated by USACE and the end user ( Owner was Ministry of Defense / Iraqi Air force)
- The project started in Nov 2009 and Completed with a successful turnover in March 2011.

This project was awarded to MEE as Design-Build project. The project includes design,
fabrication, erection construction of 4 of 245,000 liters JP8 tanks, 2 offloading systems, 3 loading systems, all piping from 2 inches up to 8 inches, instrumentation, cathodic protection, telecommunication, control panels and PLC, operation building, electricity generation and distribution system, sewer and water systems and tie-ins, concrete roads and parking, parking shades and f
ueling / refueling canopies, spill containment system, geotextile and geomembran works, concrete dikes for the tanks, fencing and gate, firefighting system and lighting system.

MEE has completed the project and turned it over to the client in March 2011 with high
satisfaction to the client. MEE responded to all warranty issues in timely and professional manner and had the close off the project done.

 